Transport & Site Work
Step 1

Pro-Fab arrives on site and verifies the dimensions of the foundation.
Step 2

The set up crew installs foam sill sealer on perimeter of foundation.
Step 3

The set up crew will adjust the dimension of the lally columns and install per plans.
Step 4

The set up crew prepares the first module for installation.
Step 5

The crane has installed a spreader bar to set the first module on the foundation.